Hi,
I have problems with hours displayed in portfolio analyzer. Sometimes,
project managers make modifications in one of their projets (like changing
the amount of hours for a given task) and after that they republish the whole
projet. After I rebuild the OLAP Cube and verify the modified hours in
portfolio analyzer of the resource center. Sometimes, the modifications are
not reflected in the portfolio analyzer and I don't understand why. Even if
I republish the projet and rebuild the Cube again.
Any idea?
Andrea
I have problems with hours displayed in portfolio analyzer. Sometimes,
project managers make modifications in one of their projets (like changing
the amount of hours for a given task) and after that they republish the whole
projet. After I rebuild the OLAP Cube and verify the modified hours in
portfolio analyzer of the resource center. Sometimes, the modifications are
not reflected in the portfolio analyzer and I don't understand why. Even if
I republish the projet and rebuild the Cube again.
Any idea?