I am trying to view my projects using a Portfolio Analyzer View. The view I
created shows the Resource Name, Work, and availability. When I open the
view, I see the resource name, but the work and availability are blank.

When I look at the resource pool and the Project Plans, there are values in
work and in availabilty. Can someone tell me why these field are not showing
in my view?

Thanks

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...f248e6f681&dg=microsoft.public.project.server
 
M

Marc Soester

Hi S Williams,

Have you actually updated your OLAP Cube after the values of the resource
have changed?
You will need to go to Admin > Manage enterprise features. Under Update
frequency you can build the cube now or set a time when the cube will need to
be rebuild.
I hope this helps
 