Is there a way for me to update my project plans with the
results of the portfolio modeler?
 
D

Dale Howard [MVP]

Jeremy --

Unfortunately, no. This is one of the key weaknesses of the Portfolio
Modeler. The tool tells you that you can theoretically finish your project
earlier by changing the resource loading of the project, but neglects to
tell you how to do it! Sorry.
 