Possible PWA Views

R

Rhonda H

Does anyone know if...
Is it possible to create a view in PWA that does not
have the Gantt Chart? I would like a view that has
several columns of data without the Gantt being on it.

Does a view exist that shows the status of enterprise
resources entering their
time againt task. We want to be able to have some type of
view or report that gives us the name of the resources who
do not enter actuals for a given week (or time period).
Any ideas how to create this?

Thanks in advance,
Rhonda H
 
G

Gary Chefetz [MVP]

Rhonda:

To your first question, the answer is no. However, Project Server 2003
allows you set the position of the divider bar so that you can create a view
that initially displays all data with the divider bar to the far right.

For your second question, go to the Resource Center and select View Resource
Assignments from the left-hand navigation pane. Then choose the timesheet
view. By applying grouping and filtering you can get the information you're
looking for.
 
J

John

A data only view is possible using Web Access Components.
There is one that creates Excel sheet. This is also
possible using a Data Access Page.
 