I'm not sure this is possible but it has been requested by
several of our project managers. We have Project Pro and
Server 2002 and are in the process of upgrading to 2003.
Desired scenario:
1. A resource updates a task on PWA that indicates that
the task has been completed early (say 2 days early in
this case).
2. The PM accepts the update and updates the project plan.
3. The PM wants all future tasks on the plan to be moved
up automatically so that they start 2 days earlier.
4. Project Server then notifies all subsequent resources
that their tasks will now start 2 days earlier.
Is this possible?
several of our project managers. We have Project Pro and
Server 2002 and are in the process of upgrading to 2003.
Desired scenario:
1. A resource updates a task on PWA that indicates that
the task has been completed early (say 2 days early in
this case).
2. The PM accepts the update and updates the project plan.
3. The PM wants all future tasks on the plan to be moved
up automatically so that they start 2 days earlier.
4. Project Server then notifies all subsequent resources
that their tasks will now start 2 days earlier.
Is this possible?