hi all, Can I display tasks predecessor in project detail views ? And if so how ?
S shoham Apr 17, 2007 #1 hi all, Can I display tasks predecessor in project detail views ? And if so how ?
D Dale Howard [MVP] Apr 17, 2007 #2 Shoham -- At the moment, you can't. The lack of this field appears to be an oversight on Microsoft's part. Perhaps it will be fixed in SP1. Hope this helps.