predecessor task from seperate project file.

J

Joe

I have two separate projects on the server using an enterprise resource pool.
How can I make the task from one project have a predecessor of a task from
the other project?
 
B

Brian K - Project MVP

Joe said:
I have two separate projects on the server using an enterprise
resource pool. How can I make the task from one project have a
predecessor of a task from the other project?

Use the Insert | Project menu item to insert both these projects into a
master project. Then link the two tasks as you would with any tasks and
then the tasks in the two projects will be linked.

--
___
Brian K
Project MVP
http://www.projectified.com

Project Server Consultant
http://www.quantumpm.com
 
Top