Predefine tasks in Enterprise global template

J

Joakim K

We have defined 4 toplevel tasks that we want to include in the Enterprise
Global template.

So far I have not managed to update the template. After saving to the server
these tasks is gone.

How do I include tasks in the Enterprise global template?

Regards
/Joakim
 
D

Dale Howard [MVP]

Joakim K --

You can't, as this is not the purpose of the Enterprise Global template.
This file serves as your organization's "library" of enterprise custom
Views, Tables, Filters, Groups, Fields, Reports, etc. It is also contains
your organization's default currency. If you wish to create a template from
which your PM's can create projects containing the four toplevel tasks,
create a new blank project, add the four tasks, click File - Save, and set
the Type as Template. Hope this helps.
 
J

Joakim K

Hi Howard

Well, it doesn't help in the way that we would like. But, distributing a mpt
via our intranet and then publish it on project server will work.

Thanks
 
Top