R
RickD
We have an instance where a PM was updating a project plan in Pro. The
changes required a Publish Changed Assignments. After publishing and saving
the plan, the PM re-opened the plan. All previously completed tasks were at
0% for both Work Complete and % Complete. We are using Managed Periods and
the plan was originally imported to Server (after temporarily turning off
Managed Periods and Timesheet Approvals). Anybody else had problems with
actuals being reduced to zero?
changes required a Publish Changed Assignments. After publishing and saving
the plan, the PM re-opened the plan. All previously completed tasks were at
0% for both Work Complete and % Complete. We are using Managed Periods and
the plan was originally imported to Server (after temporarily turning off
Managed Periods and Timesheet Approvals). Anybody else had problems with
actuals being reduced to zero?