Hi Is there a way to print out the dates of tasks on the chart. e.g. 1st August - 15th Oct? Thanks
J Joe Jun 11, 2004 #1 Hi Is there a way to print out the dates of tasks on the chart. e.g. 1st August - 15th Oct? Thanks
M Mike Glen Jun 11, 2004 #2 Hi Joe, Welcome to this Microsoft Project newsgroup Try Format/Bar Styles.../select Task in the Name column and in the Text tab, Left - select Start, and Right - select Finish. FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on ) Mike Glen MS Project MVP
Hi Joe, Welcome to this Microsoft Project newsgroup Try Format/Bar Styles.../select Task in the Name column and in the Text tab, Left - select Start, and Right - select Finish. FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on ) Mike Glen MS Project MVP