Is there a way to print out the dates of tasks on the
chart. e.g. 1st August - 15th Oct?

Thanks
 
M

Mike Glen

Hi Joe,

Welcome to this Microsoft Project newsgroup :)

Try Format/Bar Styles.../select Task in the Name column and in the Text tab,
Left - select Start, and Right - select Finish.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen