Printing Task for a day

S

SloopJohnB

My schedule has growing to 650 tasks over 24hours for a 14 day period
can I print out the tasks that are in a particuliar time period sa
0400am to 0400pm on day 5.

The printer setup of print between day 4 & 5 prints out the full 65
tasks while only 50 tasks happen in that date
 
R

Rob Schneider

Take a look a the Menu: Project/Filtered For ... the pre-built one
called "date range" may do what you want. If not, make your own by
pressing the "more filters" button. You to figure out the logic of a
filter that fields and filters defines what you mean by "that are in a
particular time period."

You can read all about how to use filters in Help.

--rms
 
R

Rod Gill

Hi,

I think you would need to adjust the timescale so only a day or two shows on
it. Project will always print the whole of a page using the date range.
Otherwise do what Rob suggested and filter the Tasks first.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
M

Michael.Tarnowski

My schedule has growing to 650 tasks over 24hours for a 14 day period,
can I print out the tasks that are in a particuliar time period say
0400am to 0400pm on day 5.

The printer setup of print between day 4 & 5 prints out the full 650
tasks while only 50 tasks happen in that date.

--
SloopJohnB
------------------------------------------------------------------------
SloopJohnB's Profile:http://forums.techarena.in/members/107024.htm
View this thread:http://forums.techarena.in/microsoft-project/1231599.htm

http://forums.techarena.in


Hi SloopJohnB,
You can set date ranges in the Print dialog box.
Hope that helps, have fun, cheers
Michael
 