B
Bernie V
I am using MSP Office 2003 and am having problems prioritizing tasks within
the project. I prioritized a task within the project as 900 working through
"Task Info" screen, but a 500 priority task is still scheduled to start
before the 900 priority task. Both have same resource identified. How do I
get the 900 priority task to start on desired date?
the project. I prioritized a task within the project as 900 working through
"Task Info" screen, but a 500 priority task is still scheduled to start
before the 900 priority task. Both have same resource identified. How do I
get the 900 priority task to start on desired date?