Hello, At Project 2007, how do I publish selected tasks or current view ? Thanks Perl
P Perl Jun 10, 2007 #1 Hello, At Project 2007, how do I publish selected tasks or current view ? Thanks Perl
N NZ Projects Jun 10, 2007 #2 Add the "Publish" column to the Gantt View then toggle between Yes/No depending on whether you want to publish or not. HTH
Add the "Publish" column to the Gantt View then toggle between Yes/No depending on whether you want to publish or not. HTH