Prject web access

C

Carla

Hi have a problem. I have the right of administrator and project leader, and
even like that I can not modify the “real End, for example†when I am using
PWA.
I will be very grateful, if you can help me to discover what I need to do to
have the right to modify information on PWA Project web access interface.
Thank
 
B

Brenda D.

I think what you are saying is you want to modify the Actual Finish Date.
That is a calculated field. If a task is finished have the resource change
the remaining work to zero. That should change to finish date to the last day
work was entered for that resource.
 