PrjMsgHlr 0x8c040012 error

S

SBelling

Does anyone know what this particular error is referring
to and what not to do to make it go away?

Thanks,
SBelling
 
J

johnny nui

i found this on google

0x8c040012

Resource account is inactive
(PJWEB_E_INACTIVE_RESOURCE)

You receive this error message if a resource account in the Microsoft
Project Server database is inactive.
 
S

SBelling

Thanks - that makes perfect sense, as we have an inactive
enterprise resource in our resource pool.

Thanks for the info.
SBelling
 