Problem affecting 1 resource

M

Mike Mahoney

Using PS2007 SP1

A task I have done many times is to change resource calendar to enter
holidays. One resource now misbehaves. After changing its calendar
MSP displays a wizard and says resource fails validation with "
Resource Name already in use" message. So cannot saved calendar
change. I can open the resource and change any other attribute but
not the calendar. Interestingly I can use Plan administartive time to
change the resource calendar for that problem resource. Any ideas how
I can "reset" this resource?

regards

Mike
 
Top