Yashrah
hi,
When i try to modify the Actual Work(in hours) field in Project Professional 2003, the Work field also changes incase the actual work is greater than the work assigned. Is there any mechanism with the help of which i can keep track of originally assigned hours as well as the actual work done on a particular task?
regards
yashrah.
When i try to modify the Actual Work(in hours) field in Project Professional 2003, the Work field also changes incase the actual work is greater than the work assigned. Is there any mechanism with the help of which i can keep track of originally assigned hours as well as the actual work done on a particular task?