Problem swirching to Gantt view from another view

B

Bill Stewart

Every time I return from any other view to Gantt, the filter turns on for compleyed tasks (as if it were a default) and I have to change the filter to showall tasks. Anybody know what's going on?
 
D

Dale Howard [MVP]

Bill --

Please try these steps:

1. Open the project in which you are having this problem
2. Click View - More Views
3. Select the Gantt Chart view and click Edit
4. Select Entry as the Table value
5. Select No Group for the Group value
6. Select All Tasks as the Filter value
7. Click OK and then click Apply
8. Save the project

Hope this helps.




Bill Stewart said:
Every time I return from any other view to Gantt, the filter turns on for
compleyed tasks (as if it were a default) and I have to change the filter to
showall tasks. Anybody know what's going on?
 