Angus Duncan
Dear all,
I've got a problem with the "export to excel" facility. I want to export
Actual costs spread across months.
For example, I have one activity with an actual cost of £9.5 and 3 months
duration. The ACWP gets exported as £9.5 PER MONTH up to the status date.
The Actual Cost figure gets exported as £9.5 for the first month and then
nothing for the remaining 2 months duration on this activity. What I would
hope to see is the £9.5 prorated across the 3 months duration of this
activity.
Does anybody have any ideas here?
Thanks and regards,
Angus Duncan
I've got a problem with the "export to excel" facility. I want to export
Actual costs spread across months.
For example, I have one activity with an actual cost of £9.5 and 3 months
duration. The ACWP gets exported as £9.5 PER MONTH up to the status date.
The Actual Cost figure gets exported as £9.5 for the first month and then
nothing for the remaining 2 months duration on this activity. What I would
hope to see is the £9.5 prorated across the 3 months duration of this
activity.
Does anybody have any ideas here?
Thanks and regards,
Angus Duncan