problem with project planing

P

Peter Simkovic

a got just one small problem.

if resource put values into his tasks timesheet into the project, the
project plan will be rescheduled. how it is possible to stop changing
project plan?
 
R

Rod Gill

Either don't accept the timesheet, or don't use timesheets!

Timesheets very accurately update the schedule with what actually happened.
So what don't you want to see happen and why?
 