M
Michael Jester
I've seen a few messages on this, looking to see if anyone
has answers. These are some of the problems I've
encountered when setting up Master/sub-projects with MS
Project Server:
1) sub-projects listed under the master project do not
expand (i.e. can't see tasks in the sub-project if it is
part of a master project)
2) similarly, resources cannot open up the subproject
individually, they can only open up the master project,
which causes problems because under #1 I said that they
can't expand the sub-project (I even tried playing games
with assigning the resource as an explicit resource to the
sub-project, and it seemed to want to keep making it a
resoure to the master project)
3) upon playing around with it further, engineers were
unable to see ANY projects or ANY tasks, and project
manager could not see any resources
If anyone has information to produce the following, it
would be helpful:
1) set up a master project with sub-projects
2) project manager can see entire master project and all
sub-projects
3) sub-projects inside master project plan can expand to
show tasks
4) project manager can see all resources
5) resources can view all of their tasks
6) resources can view sub-project plan to which they are
assigned in project center
has answers. These are some of the problems I've
encountered when setting up Master/sub-projects with MS
Project Server:
1) sub-projects listed under the master project do not
expand (i.e. can't see tasks in the sub-project if it is
part of a master project)
2) similarly, resources cannot open up the subproject
individually, they can only open up the master project,
which causes problems because under #1 I said that they
can't expand the sub-project (I even tried playing games
with assigning the resource as an explicit resource to the
sub-project, and it seemed to want to keep making it a
resoure to the master project)
3) upon playing around with it further, engineers were
unable to see ANY projects or ANY tasks, and project
manager could not see any resources
If anyone has information to produce the following, it
would be helpful:
1) set up a master project with sub-projects
2) project manager can see entire master project and all
sub-projects
3) sub-projects inside master project plan can expand to
show tasks
4) project manager can see all resources
5) resources can view all of their tasks
6) resources can view sub-project plan to which they are
assigned in project center