T
Tom Slypaw
Hi,
I have searched the forums but could not find the answer to this:
Right now I calculate productivity as such:
=IF(Q3=0,0,(Q3/M3)*8)
Q3 is units completed
M3 is hours worked
Multiplyling by an 8 hour shift gives me the productivity.
Instead of calculating at the end of the workshift, I am looking for
way to have a running total.
I have a worksheet running total individual completions (shared) as th
employees enter data.
Is there a formula I can add that would calculate if an employee begin
his shift at 7:am and has 3 completion at 9:am, and calculate th
productivity?
Thank you,
~To
I have searched the forums but could not find the answer to this:
Right now I calculate productivity as such:
=IF(Q3=0,0,(Q3/M3)*8)
Q3 is units completed
M3 is hours worked
Multiplyling by an 8 hour shift gives me the productivity.
Instead of calculating at the end of the workshift, I am looking for
way to have a running total.
I have a worksheet running total individual completions (shared) as th
employees enter data.
Is there a formula I can add that would calculate if an employee begin
his shift at 7:am and has 3 completion at 9:am, and calculate th
productivity?
Thank you,
~To