B
Bill Busby
Right now this is at the idea stage and I'd like input on where it falls on
the 'great idea' to 'you gotta be nuts' scale.
We constantly have Project Pro making adjustments to our schedule (using
fixed duration, non-effort driven) tasks as we record time updates from PWA
(PM's not allowed to make their own changes to work effort). Project Pro
tells us we can't complete the task in the time alloted and I'm gonna help
you out by changing the duration. Our PM's need to do a better job of
assessing effort but the reality is we aren't likely to close that gap
anytime soon.
Possible solution? Have each PM develop their WBS and baseline their
schedule. Based on some event like closing the project plan have a job that
compares the schedule to the baseline and resets the duration (and by default
the finish dates) to the values contained in the baseline. Thoughts?
the 'great idea' to 'you gotta be nuts' scale.
We constantly have Project Pro making adjustments to our schedule (using
fixed duration, non-effort driven) tasks as we record time updates from PWA
(PM's not allowed to make their own changes to work effort). Project Pro
tells us we can't complete the task in the time alloted and I'm gonna help
you out by changing the duration. Our PM's need to do a better job of
assessing effort but the reality is we aren't likely to close that gap
anytime soon.
Possible solution? Have each PM develop their WBS and baseline their
schedule. Based on some event like closing the project plan have a job that
compares the schedule to the baseline and resets the duration (and by default
the finish dates) to the values contained in the baseline. Thoughts?