Progress bar styles

J

John V

Hi,

I'm using 2002 Professional and am having a small problem
with the bar styles, specifically progress and Physical %
Complete.

When I set the progress bar style to Physical % Complete,
it does not display. I therefore have to use %work
complete which is close in value (most of the time,but not
always). By the way, my earned value method is set to
Physical % Complete so I'm not sure what I'm missing.

Any insight would be appreciated.

Thanks,

John
 