progress is 100% yet progress line shows only 50%

O

Odyssey 62

When I insert the "% complete" as 100% in some instances the progress line
shows the task as being behind schedule or abot 50% complet
 
J

Jonathan Sofer [MVP]

Can you also include the other % completes like "Physical % Complete" and "%
Work Complete" and see what values are in those columns?

Also, you can right click in the Gantt area and select "Bar Styles..." check
to see what the "Progress" row shows for the From and To fields.

Jonathan
 
Top