Bas Grimbergen said:
Hi John, an example with dates and durations:
The Project Start Date is november 2nd. The project has got three tasks, A,
B and C, and a summary task over Task A and Task B. Task A and Task B have a
duration of 5 days. The duration of Task C is 15 days. Task B is a successor
of Task C. Task C is a successor of Task A. The relationships are
Finish-Start.
Summary Task 25d Mon 2-11-09 Fri 4-12-09
Task A 5d Mon 2-11-09 Fri 6-11-09
Task B 5d Mon 30-11-09 Fri 4-12-09
Task C 15d Mon 9-11-09 Fri 27-11-09
The status date is today, november 18th, and the %Complete is as scheduled.
I would like to display a progress line. When i do so, the progress line
(progress point) on the summary bar is set on november 30th. The progress
line will show a peak to the right while the project is on schedule, not
ahead of schedule.
I hope the problem is clear now.
Thank you anyway for you time and replies already.
Bye, Bas
Bas,
I see Rob jumped in before I could take a look at the detail information
you provided. As Rob said, the progress line for the summary task is
correct. It is showing that 50% of the two tasks under it are complete.
Task A is complete and since Task B doesn't start until Nov 30th, the
summary progress line is shown at the end or Task A which effectively is
the beginning of Task B, namely Nov 30th. Basically the time period
shown by the summary line during which task c occurs doesn't count -
Task C isn't part of the summary line information. Remember, what you
are seeing in the Gantt is duration which is simply a span of time. And
for a summary line that can be very confusing for some users.
Users often find that Project doesn't do things quite the way they
expect. On rare occasions the difference is due to a bug but the
majority of the time it is simply a misunderstanding of how Project
works.
Hope this helps.
John
Project MVP