G
GillianHG
I'm trying to work with progress lines and online Help says lines with a peak
to the right are for tasks ahead of schedule and peaks to the left are for
tasks behind schedule. I have always thought it was the other way around. Is
this a typo in Help, or is it me??
Example:
Say in my project, I have a task are running about two days late (meant to
start Wed Jan 5 and started Friday Jan 7). I do a progress line for Jan 5 on
actuals and it goes out to my late start task on Jan 7 and then back in to
the progress line for Jan 5.
To me, that shows a point is going RIGHT. Yet according to the Help file, a
right point is a task ahead of schedule - this task is clearly behind.
Can someone please help? I'm writing some documentation for a user so I need
to make sure I get this.
to the right are for tasks ahead of schedule and peaks to the left are for
tasks behind schedule. I have always thought it was the other way around. Is
this a typo in Help, or is it me??
Example:
Say in my project, I have a task are running about two days late (meant to
start Wed Jan 5 and started Friday Jan 7). I do a progress line for Jan 5 on
actuals and it goes out to my late start task on Jan 7 and then back in to
the progress line for Jan 5.
To me, that shows a point is going RIGHT. Yet according to the Help file, a
right point is a task ahead of schedule - this task is clearly behind.
Can someone please help? I'm writing some documentation for a user so I need
to make sure I get this.