K
KenCat
Hi,
could you please assist. I have to provide an update of a consolidated
project containing 12 off sub projects. The best way to visualise any
slippage graphically was to use the progress line. Unfortunately a number of
tasks with a 100% completion are indicated as being behind schedule. I have
tried all format settings in progress lines form to no effect. Any ideas what
could be causing this ?