Progressed bars not splitting to past the status date

A

Andrew

One of my sites has just sent me a progress report where the bars which have
progress against them do not send the unused section to the other side of the
status bar as all our other projects do. any bar without progress is moved to
the other side of the status bar. I have no idea how they have managed it,
any thoughts would be appreciated. I have the tracking section to Reschedule
uncompleted work after (status date) All our programmes are based on fixed
units and do not have any constraints and are fairly well linked. This
problem has occured since the last progress which was carried out ok.

Regards

Andrew
 