M
Michael Balda
Please help. When I export my Proj 2003 data using projects export functions
and saving my data as a text tab delimited file, it sends everything that I
want it to just fine. I change the data in a program just fine. BUT when I
use Proj 2003 to import the changed text tab delimited file, Proj 2003 rounds
up my tasks durations to whole number days, example a 4 hour task is now a 1
day duration, AND it also ignores the start dates of the tasks and puts all
tasks starting at the same time. The rest of my data appears to import just
fine, my links/predecessors, resources, various text field data is all there.
Proj is for some reason ignoring my duration and dates. I will happily
share my import data if anyone would like to see it.
and saving my data as a text tab delimited file, it sends everything that I
want it to just fine. I change the data in a program just fine. BUT when I
use Proj 2003 to import the changed text tab delimited file, Proj 2003 rounds
up my tasks durations to whole number days, example a 4 hour task is now a 1
day duration, AND it also ignores the start dates of the tasks and puts all
tasks starting at the same time. The rest of my data appears to import just
fine, my links/predecessors, resources, various text field data is all there.
Proj is for some reason ignoring my duration and dates. I will happily
share my import data if anyone would like to see it.