Proj Pro/Server 2003 Summary totals not zeroing out

M

Mark T

I have zeroed out all remaining work assigned to each
resource on the task and marked the task as 100% complete.
The Summary totals for each level above the task, all the
way to the top Project Summay, still are showing non-zero
values in % Complete and Work Remaining columns?
 
D

Dale Howard [MVP]

Mark T --

It sounds like you have one or more tasks in each summary level that are not
100% complete. If you are seeing a 99% complete at each summary task, then
you have probably forgotten to mark one or more milestones as 100% complete.
Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
Top