Dino
Hi all,
We have just upgraded to Project 2003 and Project Server
2003. I have performed config of the Web interface but I
have a problem with the timesheet. Even though I have
asked that it automatically generate the period (Non
Managed periods) and the default method for reporting the
hours worked on each task is set to "Hours of work done
per day per week..." my team can't update the actuals per
day in the right pane of the timesheet. I have searched
high and low and believe I have configured it correctly -
yet the time sheet still defaults to "Actual work done and
work remaining"
Please can anyone provide me with some tips or checks to
make to resolve this?
Much appreciated.
We have just upgraded to Project 2003 and Project Server
2003. I have performed config of the Web interface but I
have a problem with the timesheet. Even though I have
asked that it automatically generate the period (Non
Managed periods) and the default method for reporting the
hours worked on each task is set to "Hours of work done
per day per week..." my team can't update the actuals per
day in the right pane of the timesheet. I have searched
high and low and believe I have configured it correctly -
yet the time sheet still defaults to "Actual work done and
work remaining"
Please can anyone provide me with some tips or checks to
make to resolve this?
Much appreciated.