I have one user who, when they open up project files, gets different
dates in the Start and Finish columns than everyone else. We
discovered this when one project plan was off by 5 months. When the PM
opens the project, the dates are correct. The dates are also correct
when I open it. But when this particular user opens it, the Start and
Finish columns have the wrong data!
I checked to see if anything in the Tools > Options menu might help,
but everything was the same as the default and the same as mine. This
isn't a power user, so I doubt anything fancy has been done to the
project. The odd thing is all the other columns are correct -- %
complete, actual work, remaining work, etc. Only the dates have
changed.
Since the problem seems to be with the client (or perhaps client
machine?), what settings or issues might cause this error? Or does
this sound like a corrupt client that needs to be reinstalled?
dates in the Start and Finish columns than everyone else. We
discovered this when one project plan was off by 5 months. When the PM
opens the project, the dates are correct. The dates are also correct
when I open it. But when this particular user opens it, the Start and
Finish columns have the wrong data!
I checked to see if anything in the Tools > Options menu might help,
but everything was the same as the default and the same as mine. This
isn't a power user, so I doubt anything fancy has been done to the
project. The odd thing is all the other columns are correct -- %
complete, actual work, remaining work, etc. Only the dates have
changed.
Since the problem seems to be with the client (or perhaps client
machine?), what settings or issues might cause this error? Or does
this sound like a corrupt client that needs to be reinstalled?