Edward --

I presume that you mean you want to prevent team members from reporting
progress on tasks in a completely project. If this is the case, open the
project and then click Tools - Build Team from Enterprise. For each member
of the project team, set the Booking value to Proposed and then click the OK
button. Click Collaborate - Publish - All Information and this will remove
the tasks for that project from each team member's View My Tasks page in
PWA. Hope this helps.
 
E

Edward Wang

Dale, thanks!

A further question, by the way you introduced, could we keep the original
data the resource reported? We usually use the data captured by OLAP Cube

Edward
 
D

Dale Howard [MVP]

Edward --

Using the procedure I detailed, you will not lose any resource data. Hope
this helps.
 