Project 2003 ---- How to help other team member to fill time repor

E

Edward Wang

Hi, How could resource manager or secretary to help team members to fill the
time report when they could not log in the system.
 
L

Langhorne

We've done this pretty easily using the "Adjust Actuals" function under
Resources, and then printing the timesheet. The only downside is that the
resulting timesheet gives the name of the person who made the change, not the
person whose hours were changed (which always struck me as being strange...).
Maybe I'm misunderstanding the question.

- Langhorne
 
Top