C
Cazzy123
Sorry if this post doubles up but I am not sure that the first one went
through.
I have made a copy of the standard calendar for my project and using the
Change Working Times option have added a few non working days. However,
although they show as Exeption days in the calendar when i go to my Gantt
chart they are still showing as a working day.
I have double checked under Project information that my project is using the
copy standard calendar.
Please could you let me know why it is not showing in my Gantt chart.
Thanks
through.
I have made a copy of the standard calendar for my project and using the
Change Working Times option have added a few non working days. However,
although they show as Exeption days in the calendar when i go to my Gantt
chart they are still showing as a working day.
I have double checked under Project information that my project is using the
copy standard calendar.
Please could you let me know why it is not showing in my Gantt chart.
Thanks