Project 2007 Ordering materials

M

Mark H

Can you organise for project 2007 to automatically order materials at
particular times i.e. via fax or e mail 3 days prior to the given materials
being required on site ?
 
R

Rod Gill

Out of the box, no. However via custom coding anything is possible. having
said that, project is not a job costing tool, nor is it one for managing all
your materials from order to installation, though of course you can specify
materials.

I think you would be better off looking for a job costing tool that can
handle quotes and orders as well.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 