Project 2007, PWA My Task View

K

Karen M

Project 2007, PWA My Task View, in the Assignment Detail screen, the "Work"
is displaying three decimal places (ex: 5.285h). Project schedule displays
two decimal places (5.28). Is there a way to configure the view in PWA to
just show two (or hopefully just one) decimal place? I use a fixed work
schedule. Thank you.
 
J

Jonathan Sofer [MVP]

You cannot configure the "Assignment Details" view in that way.

Jonathan
 
K

Karen M

Why then are some of the hours rounding to no decimal places while others are
displaying three decimal places, and others two decimal places? We're all
using the same project schedule template, resource pool, and enterprise
calendar. Thanks for any help.
 