Project 2007 Resourse Task Updates - No summary tasks

D

dean.benzion

We just deployed 2007 after using 2003 for the past 18 months. I had
my first resourse do his updates today but there are no summary tasks
anymore. It just shows the name of the project then lists out all the
tasks. Sometimes though tasks are duplicated from section to section
in my schedules so the resurce can't tell what section a task is
from. I can't seem to be abel to find a setting that adds the task
summary line back into the update area. Does anyone know how to fix
that? This is a BIG problem for me.

Thanks
 
D

Dale Howard [MVP]

Dean --

There is no fix. The feature is by design, for whatever reason. The reason
can click the name of the task to see summary task information at the top of
the Detailed Assignment page, but its presentation is not very useful,
however. Hope this helps.
 
Top