Project 2007-tracking by time of day

M

Maria Maz

Can you track a project by time of day. I have a project that will only span
approx 5 days, but is dependent on a multitude of tasks within a given day.
I need to track tasks by the minute or hour, not by day.

I can change the duration to minutes, but that's as far as I've gotten.

Can anyone help me with this?

Thanks,
Maria
 
M

Mike Glen

Hi Maria,

Welcome to this Microsoft Project newsgroup :)

Try Tools/Options.../View tab and select the Date Format to include times of
the day. That should help a bit. Let us know what else might be of help.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 