project 2007 - Workspace permissions through RBS

P

Prasad Weerasinghe

EPM project workspaces do not seam to inherit the RBS structure for access. Do only team members have access to open the Project workspaces, is it not possible to inherit this through the RBS for top level resources?
 
M

Marc Soester [MVP]

Prasad,

please note that if you have a team member associated to the Project
Schedule means that the team member only has read access. Only if you assign
a resource to a task within the project schedule will the resource have
contributor rights to the workspace.
Hope this helps
Marc
 