Project add-in for Outlook

A

agreen

Hi all,

I am using Project Server 2007 and I have successfully installed Outlook
plug in for project server. When I try to connect to my site it is giving
this error message:

"The server was enabled to process the last request"

Let me know do I need to do some other setting to work it successfully?
 
J

Jonathan Sofer

Not sure if this helps but I thought you might like to know that if you are
using the Outlook interface for Microsoft Office Project 2007 you need to
make sure that there are no fields (Resource or Task) which have the @Roll
down to assignments rows@ option checked. The standard Cost Type, Team Name
and RBS fields have this set by default and need to be changed. Otherwise
you get a SOAP error. Microsoft is aware of the problem, but no hotfix yet.

Jonathan
 