O
okie2000
We use project to schedule our personnel assignments (we are a service
origination). (2009 Field Projects)
our subtask are Month, then project assignment. Resources could be 1 to 10
folks for a fixed duration (8hrs in/out (tarvel) and 11 hrs work each day)
Sunday to saturday.
I would like to have standard office hours assigned at 8 hrs (m-f).
Project hrs are assigned at 11 hrs /day (sun-sat);
and travel hrs are assigned at 8 hrs/day (s-s).
I have changed the “optionsâ€, calendar, default setting to;
Hours per day; 11
Hrs per week; 77; days per month; 31.
Cant seam to get the resource hours correct when assigned. Should I create
custom “Working Time Calendarsâ€
Office Time, 8am to 5 pm (m-f)
Travel time, 8am to 5 pm (s-s)
Project time 7am-7pm (s-s).
When a resource is added to a task they get 8 hrs work time no mater the
assignment. I need the above hrs by time type and know I am missing
something.
And assign them for each direct task?
origination). (2009 Field Projects)
our subtask are Month, then project assignment. Resources could be 1 to 10
folks for a fixed duration (8hrs in/out (tarvel) and 11 hrs work each day)
Sunday to saturday.
I would like to have standard office hours assigned at 8 hrs (m-f).
Project hrs are assigned at 11 hrs /day (sun-sat);
and travel hrs are assigned at 8 hrs/day (s-s).
I have changed the “optionsâ€, calendar, default setting to;
Hours per day; 11
Hrs per week; 77; days per month; 31.
Cant seam to get the resource hours correct when assigned. Should I create
custom “Working Time Calendarsâ€
Office Time, 8am to 5 pm (m-f)
Travel time, 8am to 5 pm (s-s)
Project time 7am-7pm (s-s).
When a resource is added to a task they get 8 hrs work time no mater the
assignment. I need the above hrs by time type and know I am missing
something.
And assign them for each direct task?