I have an issue with the project information that gets
included when the Olap cubes are generated.
If a PM publishes a new project, with assignments and
approves some actuals entered by resources. Then we run
the OLAP cube which goes through. But when the PM goes
into Portfolio Analyzer, they can see the project in the
list but when selected non of the detail is included?
This information does tend to appear eventually but it
can sometimes takes several generations of the cube
before it appears.
Any ideas or suggested checks for this?
Thanks
Alex
included when the Olap cubes are generated.
If a PM publishes a new project, with assignments and
approves some actuals entered by resources. Then we run
the OLAP cube which goes through. But when the PM goes
into Portfolio Analyzer, they can see the project in the
list but when selected non of the detail is included?
This information does tend to appear eventually but it
can sometimes takes several generations of the cube
before it appears.
Any ideas or suggested checks for this?
Thanks