Project Center and TimeSheet

  • Thread starter Mindaugas Bliûdþius
  • Start date
M

Mindaugas Bliûdþius

Hi,

Is it possible in project center to see timesheet instead of grantt?

I need in project center to see actual work and actual cost for each project
for specified period (also how to do this?).

In MS Project i use Task usage view and set timescale by month and can see
how much we used time and money in each month for project.


Thank's
 
D

Dale Howard [MVP]

Mindaugas --

Your Project Server administrator can create a custom Portfolio Analyzer
view for this purpose. Hope this helps.
 