Project Center View - Baseline Gantt Missing

R

rayis

One of the project centre views is ' Tracking
This view uses the ' Tracking (Project Center) ' Gantt chart format

When I use this view it works fine (displays current gantt an
baseline gantt

But when I used the ' Tracking (Project Center) ' Gantt chart wit
other project centre views, I can see only the current gantt no
baseline gantt

Can someone explain this ? (I hope my scenario is clearly explained

Many thank
 
R

Reid McTaggart

Perhaps you have not defined those views to include the baseline start and
finish dates that are needed in order to display the information in the gantt
chart. If the data is not there it cannot be displayed.
 
R

rayis

Reid

You are the man !!!
I don't have words to express my sincere thanks to your perfec
solution
I was trying to show this gantt for the past 2-3 days but failed
All my views were contain only Baseline Finish not the Baselin
Start
Now it is working fine

Regard
 
Top