K
Kevin Newman
Why would MSProject create a new "Standard" calendar every time a project is
opened?
The "Standard" calendar is not associated at the Project, Resource, or Task
level, but when I open the Organizer I see the appropriate calendars for the
Project and Resources, a default entry of Standard, Then Standard1,
Standard2, etc....
Like this:
6d 20h
7d 24h
Standard
Standard1
Standard2
Standard3
Standard4
I have seen as many as 40 Standard calendars on a single project. I can
delete the extraneous calendars in the Organizer without any error messages,
Save and Close the project and when I re-open it they are all back, plus one
more.
This doesn't happen on "Save", just when the project is opened.
The only work around I have been able to use is to copy the resources into a
new project, then copy the tasks, delete the old project and save the new
project to the old name. Then it doesn't re-occur.
What could be causing this behavior?
How can I fix it?
opened?
The "Standard" calendar is not associated at the Project, Resource, or Task
level, but when I open the Organizer I see the appropriate calendars for the
Project and Resources, a default entry of Standard, Then Standard1,
Standard2, etc....
Like this:
6d 20h
7d 24h
Standard
Standard1
Standard2
Standard3
Standard4
I have seen as many as 40 Standard calendars on a single project. I can
delete the extraneous calendars in the Organizer without any error messages,
Save and Close the project and when I re-open it they are all back, plus one
more.
This doesn't happen on "Save", just when the project is opened.
The only work around I have been able to use is to copy the resources into a
new project, then copy the tasks, delete the old project and save the new
project to the old name. Then it doesn't re-occur.
What could be causing this behavior?
How can I fix it?