Project Delay

S

Sumit

Hi,
I've a question on calculating project delay.
We calculate task delay as % complete / number of days into the task
(difference of start and current date) against task duration

To replicate this to project level I was planning to use "Actual work" /
(Baseline work - remaining work)...

Would this be the right approach to do this or there is a better way?
Primarily I want to see comparison of how much work "should" have been done
according to the baseline plan V/s how much "has" been done.

Regards,
Sumit.
 
G

Guidho

For the first calculation, you need to use number of WORKING days.

For the second question:
Am I right that you want to have the baseline work timephased?
If so, you would need to create a macro for calculating the difference
between baseline work until now vs actual work until now.

Guidho
 