Project duration in hours

D

Donna

I have a project that has hour sensitive durations. How
do I display the start time rather than start date. I
can display this information on the gantt
 
D

Dale Howard [MVP]

Donna --

Open the project in question, then click Tools - Options - View. Click the
Date Format drop-down list and pick the format that shows time only. In
Project 2003, the format is called "12:33 PM". Click OK and this should
address your situation. Hope this helps.
 
D

Donna

Dale,

Thanks.

Is there a way to have both the date and time? My project
is 176 hours over 7 days. When selecting the format for
time, I lost the display of date. When selecting the
cell the date appears along with the time, but does not
stay viewable.
 
D

Dale

Please disregard. Selected drop down that provides
both. Thanks so much for your help.
Donna
 
D

Dale Howard [MVP]

Donna --

Complete the same steps as previously and pick the Date/Time that is the
second item from the top of the list of date formats. Hope this helps.
 