Project Earned Value in Portfolio Analysis

S

ST

Is possible to get "project level" BCWP (EV) out of Portfolio Analyzer?

I can get BCWS by using Budgeted Cost (with an S-Curve).
I can get ACWP by using Actual Cost (with an S-Curve)

Is there anyway to get project level BCWP (Earned Value) out of Portfolio
Analyzer without having to extend the cube (as per "Project Server 2003:
Portfolio Analyzer OLAP Extensions")?

/Spiro Theopoulos
 
M

Marc Soester [MVP]

Hi ST,

no you will need to extend the OLAP cube, or alternetafly you could use the
PRoject Server Report DB to create your earned value report
Hope this helps
 
Top